January 29, 2008

 

 

 

Henry Baggett, Director of Schools

Oneida Special School District

P. O. Box 4819

Oneida, Tennessee   37841

 

Re:       Air Conditioning Gymnasium

            Oneida High School

 

Dear Sir:

 

I am following up on your request for a proposal to air condition the High School Gym, Phases of the project and the time required are estimated as follows:

            Design – 60 Days

            TN Fire Marshal Review – 30 Days +

            Bidding for Construction Bids – 30 Days

            Construction

                        -Procure Materials – 60 Days

                        -Installation – 30 Days

 

Based upon past similar projects, I believe the preferred design solution will be a roof top unit to be located above the locker room/dressing room areas and exposed ducts in the gym.  The estimated construction cost of this project is $225,000.00.

 

We propose to provide all required Architectural and Engineering Services for the fee of six percent (6%) of the cost of construction.

 

Please let me know if I can be of further assistance.

 

Sincerely,

 

 

 

P. Neal Richardson, Treasurer

 

PNR/gh